Document Details
Name of Department/Committee : CED 54
Document Number : CED 54 ( 14913)
Document Title [English] : Preliminary draft for Cold-reduced steel wire for the manufacture of welded fabric for concrete reinforcement - Specification
Document Title [Hindi] : कंक्रीट प्रबलन के लिए वेल्डेड फैब्रिक के निर्माण हेतु अतप्त लघुकृत इस्पात की तार - विशिष्टि का प्रारंभिक मसौदा
Document Type : New
Language : English
Priority : 3
ICS Code : 77.140.15; 91.080.40
Date of Project Approval : 27-08-2018
Standards to be Superseded :


Classification Details
Group : Metals, Alloys and Metal Products (including Steel Products)
Sub Group : Steel Products for Concrete Reinforcement
Sub Sub Group : Steel Reinforcement for Reinforced and Prestressed Concrete Constructions
Aspects : Product Specification
Risk : High
Certification : Voluntary Certification
Short Commom Man's Title : Cold-reduced steel wire
ITCHS Code :
Ministry :
  • Ministry of Steel
  • Ministry of Housing and Urban Affairs
Sustainable development Goals :
Degree of Equivalence : Not Equivalent
Identical/Equivalent Standards : ISO 10544
Organization Type: ISO

Sl.No. Synosis Points
1 It covers cold reduced steel wire, especially used for the manufacture of wire mesh for reinforcement of concrete. The welded wire mesh made using these wires are being used for graded sloped floor, false ceilings, etc.
2 It covers plain, ribbed and indented cold-reduced steel wires of strength grades 500 N/mm2 and 550N//mm2. The production process is at the discretion of the manufacturer.
3 These wires are cold reduced from wire rods by passing them through dies/rollers which allow to provide ribs/indentations in the process.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 08-02-2020 30-06-2020 31-08-2021 30-11-2021 MADHURIMA MADHAV 17-05-2021
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 27-08-2018 -------
2 P-Draft 17-01-2020 Covering letter generated -------
3 P-Draft 17-01-2020 Duration : Days CED 54, -------
4 Skipped to W-Draft 25-05-2021 Stage-Changed -------
5 WC Draft 25-05-2021 Duration : 31 Days
Submitted for HOD approval
-------
6 WC Draft 25-05-2021 WC approved by HOD
CEDC  CED 02, CED 13, CED 53, MTD 04, -------