Document Details |
|||||
Name of Department/Committee : | CED 43 | ||||
---|---|---|---|---|---|
Document Number : | CED 43 ( 18748) | ||||
Document Title [English] : | Design and construction of machine foundations Code of practice: Part 4 Foundations for hammers and presses [Revision of IS 2974 (Parts 1 to 5) | ||||
Document Title [Hindi] : | मशीनों की नींव का डिज़ाइन एवं निर्माण - रीति संहिता: भाग 4 हथौड़ों और प्रेस के लिए नींव [IS 2974 (भाग 1 से 5) का पुनरीक्षण] | ||||
Document Type : | Revision | ||||
Language : | English | ||||
Priority : | 3 | ||||
ICS Code : | 93.020 | ||||
Date of Project Approval : | 14-11-2018 | ||||
Standards to be Revised : |
|
||||
Standards to be Superseded : |
|
Classification Details |
|
Group : | Civil Engineering Design and Construction |
Sub Group : | Foundation, underground structures, soil and rock mechanics |
Sub Sub Group : | Foundation Engineering |
Aspects : | Code of Practice |
Risk : | High |
Certification : | Not Certifiable |
Short Commom Man's Title : | Machine Foundation |
ITCHS Code : | NA |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | It covers design and construction of hammer foundations subjected to repeated impacts and press foundations subjected to impulsive loading. Foundations for the following machines are covered by this standard: a) Hammers: 1) Single action and counter blow hammers; 2) High energy rate machines and impactors; and 3) Ring rolling mills hammers. b) Presses: 1) Hydraulic and mechanical presses; 2) Presses with supported mandrel; and 3) Multiple ram presses. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 14-11-2018 | ------- | ||
2 | P-Draft | 10-01-2022 | Covering letter generated | ------- | |
3 | P-Draft | 10-01-2022 | Duration : 20 Days | CED 43, CED 43, CED 43 : P8, | ------- |
4 | Skipped to W-Draft | 23-02-2022 | Stage-Changed | ------- | |
5 | WC Draft | 23-02-2022 | Duration : 36 Days Submitted for HOD approval Remarks : As no comments were received on the P draft based on the recommendation of the Convener of the concerned Panel the Chairman of the Committee approved the Wide Circulation of the draft for public comments |
------- | |
6 | WC Draft | 23-02-2022 | WC approved by HOD |
CEDC MED 28, CED 43 : P8, | ------- |