Name of Department/Committee : | WRD 14 | ||||
---|---|---|---|---|---|
Document Number : | WRD 14 ( 18185) | ||||
Document Title [English] : | CODE OF PRACTICE FOR DESIGN OF TUNNELS CONVEYING WATER PART 4 STRUCTURAL DESIGN OF CONCRETE LINING IN ROCK | ||||
Document Title [Hindi] : | पानी पहुंचाने वाली सुरंगों के डिजाइन के लिए रीति संहिता भाग 4 चट्टान में कंक्रीट अस्तर की संरचनात्मक डिजाइन | ||||
Document Type : | Revision | ||||
Language : | English | ||||
Priority : | 3 | ||||
ICS Code : | 93.160 | ||||
Date of Project Approval : | 15-09-2021 | ||||
Standards to be Revised : |
|
||||
Standards to be Superseded : |
|
Classification Details |
|
Group : | Civil Engineering Design and Construction |
Sub Group : | Hydraulic and other related structures |
Sub Sub Group : | Water Conductor Systems |
Aspects : | Code of Practice |
Risk : | Low |
Certification : | Not Certifiable |
Short Commom Man's Title : | Design of Concrete Lining in Tunnels |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : |
|
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | a) Criteria for depth of the grout holes is modified in pressure grouting. b) Fig. 1 which shows typical section of concrete lined tunnel showing A-line and B-line has been updated. c) Structural steel has been omitted from definition of minimum excavation line (A-line) d) Criteria for backfill grouting has been updated. e) Criteria for design for external water pressure has been updated |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 15-09-2021 | ------- | ||
2 | P-Draft | 11-10-2021 | Covering letter generated | ------- | |
3 | P-Draft | 11-10-2021 | Duration : 30 Days | WRD 14, | ------- |
4 | Skipped to W-Draft | 20-10-2022 | Stage-Changed | ------- | |
5 | WC Draft | 20-10-2022 | Duration : 60 Days Submitted for HOD approval |
------- | |
6 | WC Draft | 20-10-2022 | WC rejected by HOD Remarks: EDITORIAL |
------- | |
7 | WC Draft | 20-10-2022 | Duration : 60 Days Submitted for HOD approval |
------- | |
8 | WC Draft | 20-10-2022 | WC approved by HOD |