Document Details |
|
Name of Department/Committee : | MTD 24 |
---|---|
Document Number : | MTD 24 ( 22071) |
Document Title [English] : | COLD APPLIED POLYETHYLENE POLYOLEFIN TAPE COATING FOR STEEL WATER PIPELINES - SPECIFICATION |
Document Title [Hindi] : | स्टील की पानी की पाइपलाइनों के लिए कोल्ड एप्लाइड (पॉलीथीलीन / पॉलीओलफिन) टेप कोटिंग - विशिष्टता |
Document Type : | New |
Language : | English |
Priority : | 3 |
ICS Code : | 25.220.01 |
Date of Project Approval : | 11-12-2021 |
Standards to be Superseded : |
Classification Details |
|
Group : | Metals, Alloys and Metal Products (including Steel Products) |
Sub Group : | Anti-corrosion products |
Sub Sub Group : | Code of Practice & Glossary on corrosion protection |
Aspects : | Code of Practice |
Risk : | None |
Certification : | None |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Indigenous |
Identical/Equivalent Standards : | |
Organization Type: |
Sl.No. | Synosis Points | |
1 | This draft standard is being formulated to serve as a guide for corrosion protection of underground mild steel pipelines by using cold applied polyethylene/polyolefin tape coating systems with the reasoning and proven performance that if the metal can be isolated with the surrounding earth, corrosion is controlled. This standard defines cold-applied tape coating systems in terms of its performance or its ability to provide long terms corrosion protection. This standard is intended for use in exterior coating of steel pipelines for underground or underwater installation under normal conditions. This standard is based on best- known experience, but is not intended for unqualified use under all conditions. Cold applied tape coating systems usage for any installation must be reviewed by the purchaser. | |
2 | If an extended period of aboveground storage of coated pipe is anticipated, the ability of coating to resist degradation by UV light and other atmospheric and environmental conditions should be considered. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 11-12-2021 | ------- | ||
2 | P-Draft Waived | 10-03-2023 | Draft was circulated to the committee vide mail for seeking their comments. The committee in its 19th meeting decided to send this draft for wide circulation. | ------- | |
3 | WC Draft | 10-03-2023 | Duration : 30 Days Submitted for HOD approval |
------- | |
4 | WC Draft | 10-03-2023 | WC rejected by HOD Remarks: Please modify as discussed |
------- | |
5 | WC Draft | 13-03-2023 | Duration : 30 Days Submitted for HOD approval |
------- | |
6 | WC Draft | 13-03-2023 | WC approved by HOD |
MTDC | ------- |