Document Details
Name of Department/Committee : TED 14
Document Number : TED 14 ( 22364)
Document Title [English] : SPACE SYSTEMS EXPERIENCE GAINED IN SPACE PROJECTS LESSONS LEARNED PRINCIPLES AND GUIDELINES
Document Title [Hindi] : अंतरिक्ष प्रणाली - अंतरिक्ष परियोजनाओं में प्राप्त अनुभव (सीखा सबक) - सिद्धांत और दिशानिर्देश
Document Type : New
Language : English
Priority : 3
ICS Code : 49.140
Date of Project Approval : 27-04-2023
Standards to be Superseded :


Classification Details
Group : Transport and Related Products
Sub Group : Aircraft equipments and air cargo handing
Sub Sub Group : Aircraft accessories & Fittings
Aspects : Process Specification
Risk : None
Certification : Voluntary Certification
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Civil Aviation
Sustainable development Goals :
Degree of Equivalence : Identical under dual numbering
Identical/Equivalent Standards : ISO 16192: 2017
Organization Type: ISO

Sl.No. Synosis Points
1 This draft Indian Standard is identical with ISO 16192: 2017 ‘Space Systems — Experience Gained In Space Projects (Lessons Learned) — Principles And Guidelines’
2 ISO 16192:2017 outlines lessons learned principles and guidelines that are applicable in all space project activities (management, technical, quality, cost and schedule). The application of this document is intended to be included in the supplier quality management system, but can be tailored in individual contracts as agreed by the customer and supplier, depending on: - the content of each project (size, technological level and novelty, particular organization, participants, etc.); - the interest and usefulness of the related information. The lessons learned information can result from any situation which might be encountered in similar contexts for future projects, i.e.: - undesirable experiences that need to be avoided; - strategies, rules, principles of design, validation, tests and operations that proved to be successful or necessary. ISO 16192:2017 neither endorses nor recommends the transmission of company proprietary information to external entities as part of a lessons

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 27-04-2023 27-09-2023 12-12-2023 27-04-2024 SHRI SHIVAM AGGARWAL 27-04-2023
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 27-04-2023 -------
2 P-Draft Waived 27-04-2023 During 26th SC meeting it was decided to wide circulate the document for 60 days. -------
3 WC Draft 27-04-2023 Duration : 60 Days
Submitted for HOD approval
-------
4 WC Draft 23-05-2023 WC rejected by HOD
Remarks: Please make corrections in the letter
-------
5 WC Draft 06-06-2023 Duration : 60 Days
Submitted for HOD approval
-------
6 WC Draft 07-06-2023 WC approved by HOD