Document Details
Name of Department/Committee : LITD 03
Document Number : LITD 03 ( 23483)
Document Title [English] : Connectors for electronic equipment - Part - 4 Tests and measurements - Section - 1: Voltage stress tests - Test 4a: Voltage proof
Document Title [Hindi] : इलेक्ट्रॉनिक उपकरणों के लिए कनेक्टर - भाग - 4 परीक्षण और माप- अनुभाग - 1: वोल्टेज तनाव परीक्षण - परीक्षण 4ए: वोल्टेज प्रूफ
Document Type : New
Language : English
Priority : 3
ICS Code : 31.220.10
Date of Project Approval : 25-08-2023
Standards to be Superseded :


Classification Details
Group : Electronic and Telecom equipments, components and devices
Sub Group : Power system control and communication
Sub Sub Group : Power System Control and Communications
Aspects : Code of Practice
Risk : Low
Certification : Not Certifiable
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Electronics and Information Technology
Sustainable development Goals :
Degree of Equivalence : Identical under single numbering
Identical/Equivalent Standards : IS/IEC 60512-4-1 : 2003
Organization Type: IEC

Sl.No. Synosis Points
1 This part of IEC 60512, when required by the detail specification, is used for testing connectors of electronic equipment within the scope of IEC technical committee 48. This test may also be used for similar devices when specified in a detail specification.
2 The object of this test is to define a standard test method to determine the ability of a component to withstand specified test voltages applied in a specified manner.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 04-09-2023 04-02-2024 19-04-2024 03-09-2024 MS. ALISMITA KHAG 04-09-2023
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 25-08-2023 -------
2 P-Draft Waived 04-09-2023 P-Draft waive -------
3 WC Draft 04-09-2023 Duration : 60 Days
Submitted for HOD approval
Remarks : Attached Wc Draft Please provide inputs
-------
4 WC Draft 05-09-2023 WC approved by HOD
LITDC  LITD 03, -------
5 WC Draft 22-11-2023 Duration : 30 Days
Submitted for HOD approval
Remarks : The committee has been decided to recirculate the WC draft comments for the period of one month
-------
6 WC Draft 12-12-2023 WC approved by HOD
LITDC  LITD 03, -------