Document Details
Name of Department/Committee : LITD 03
Document Number : LITD 03 ( 23487)
Document Title [English] : Connectors for electronic equipment Part - 4 Tests and measurements Section - 3: Voltage stress tests - Test 4c: Voltage proof of pre-insulated crimp barrels
Document Title [Hindi] : इलेक्ट्रॉनिक उपकरणों के लिए कनेक्टर भाग - 4 परीक्षण और माप अनुभाग - 3: वोल्टेज तनाव परीक्षण - परीक्षण 4सी: प्री-इंसुलेटेड क्रिंप बैरल का वोल्टेज प्रमाण
Document Type : New
Language : English
Priority : 3
ICS Code : ICS 31.220.10
Date of Project Approval : 25-08-2023
Standards to be Superseded :


Classification Details
Group : Electronic and Telecom equipments, components and devices
Sub Group : Power system control and communication
Sub Sub Group : Power System Control and Communications
Aspects : Code of Practice
Risk : Low
Certification : Not Certifiable
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Electronics and Information Technology
Sustainable development Goals :
Degree of Equivalence : Identical under single numbering
Identical/Equivalent Standards : IS/IEC 60512-4-3 : 2002
Organization Type: IEC

Sl.No. Synosis Points
1 This part of IEC 60512, when required by the detail specification, is used for testing electromechanical components within the scope of IEC technical committee 48. This test may also be used for similar devices when specified in a detail specification.
2 The object of this test is to detail a standard method to determine the ability of pre-insulated crimp barrels to withstand the crimp operation without damage to the insulation.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 04-09-2023 04-02-2024 19-04-2024 03-09-2024 MS. ALISMITA KHAG 04-09-2023
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 25-08-2023 -------
2 P-Draft Waived 04-09-2023 P-Draft waive -------
3 WC Draft 04-09-2023 Duration : 60 Days
Submitted for HOD approval
Remarks : Wc Attached Please provide inputs and comments
-------
4 WC Draft 05-09-2023 WC approved by HOD
LITDC  LITD 03, -------
5 WC Draft 22-11-2023 Duration : 30 Days
Submitted for HOD approval
Remarks : The committee has been decided to recirculate the WC draft comments for the period of one month
-------
6 WC Draft 12-12-2023 WC approved by HOD
LITDC  LITD 03, -------