Document Details
Name of Department/Committee : TED 18
Document Number : TED 18 ( 23640)
Document Title [English] : Cutter Suction Dredge Component - Specification Part 2 : Suction pipe
Document Title [Hindi] : कटर सँक्शन ड्रेज संघटक - विशिष्टि भाग 2: सँक्शन पाइप
Document Type : Revision
Language : English
Priority : 3
ICS Code : 47.060
Date of Project Approval : 29-12-2021
Standards to be Revised :
Sl.No. Is No & Year
1 IS 10854 : Part 2: 1984
Standards to be Superseded :


Classification Details
Group : Transport and Related Products
Sub Group : Shipbuilding and Marine engineering
Sub Sub Group : Dredge Components
Aspects : Product Specification
Risk : Low
Certification : Voluntary Certification
Short Commom Man's Title : Dredge suction pipe
ITCHS Code :
Ministry :
  • Ministry of Shipping
Sustainable development Goals :
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 This standards specifies the requirements of the suction pipe as a component in the cutter suction dredgers.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 22-09-2023 22-02-2024 07-05-2024 22-09-2024 SHARAD KUMAR 22-09-2023
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 29-12-2021 -------
2 P-Draft 22-09-2023 Covering letter generated -------
3 P-Draft 22-09-2023 Duration : 60 Days TED 18, -------
4 Skipped to W-Draft 30-11-2023 Stage-Changed -------
5 WC Draft 30-11-2023 Duration : 60 Days
Submitted for HOD approval
Remarks : The document was approved for wide circulation during 23rd meeting held on 23 November 2023
-------
6 WC Draft 30-11-2023 WC rejected by HOD
Remarks: Please make the necessary corrections as discussed
-------
7 WC Draft 01-12-2023 Duration : 60 Days
Submitted for HOD approval
Remarks : Necessary corrections done
-------
8 WC Draft 01-12-2023 WC approved by HOD
TEDC   -------