Document Details
Name of Department/Committee : MTD 15
Document Number : MTD 15 ( 23765)
Document Title [English] : Refractory test-piece preparation Gunning refractory panels by wet gunning techniques
Document Title [Hindi] : ABD
Document Type : New
Language : English
Priority : 3
ICS Code : ICS 81.080
Date of Project Approval : 20-06-2023
Standards to be Superseded :


Classification Details
Group : Metals, Alloys and Metal Products (including Steel Products)
Sub Group : Refractory products
Sub Sub Group : Code of practice, sampling on refractory
Aspects : Code of Practice
Risk : None
Certification : Not Certifiable
Short Commom Man's Title : Refractory test-piece preparation of Gunning refractory panels by wet gunning techniques
ITCHS Code :
Ministry :
Sustainable development Goals :
Degree of Equivalence : Identical under dual numbering
Identical/Equivalent Standards : ISO 18886:2016
Organization Type: ISO

Sl.No. Synosis Points
1 This Draft Indian Standard specifies the procedures for the preparation of test pieces from refractory materials by wet gunning at ambient temperatures. The test pieces are for the determination of properties on wet-gunned products prepared under either “standard conditions” (as required for quality assurance or product development) or “site conditions. In the case of “site conditions”, the purpose of the testing is to establish the properties pertaining to a given installation or a given set of installation conditions. In this case, the gunned panel is obtained during the on-site installation. Such parameters as activator addition (type, amount, method of addition), conveying pressure and curing conditions (temperature, orientation of the panel) applying during the preparation of the panel are as near as possible to the same parameters pertaining to the site installation.
2 This procedure applies to refractory materials that can be transported through a gunning hose after having been mixed with the total water requirement for material placement. The consistency of these materials (see 7.5) is typically such that they would be suitable for placement by casting were they not to be transported through the gunning hose and applied by spraying.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 11-10-2023 11-03-2024 26-05-2024 11-10-2024 Mr. SAAQIB RAAHI 11-10-2023
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 20-06-2023 -------
2 P-Draft Waived 11-10-2023 Adoption of ISO standard as new Indian Standard. -------
3 WC Draft 12-10-2023 Duration : 62 Days
Submitted for HOD approval
-------
4 WC Draft 12-10-2023 WC approved by HOD
MTDC  MTD 15, -------