Document Details
Name of Department/Committee : TED 16
Document Number : TED 16 ( 23300)
Document Title [English] : Bicycle — Front Forks — Specification
Document Title [Hindi] : साइकिल — सामने के कांटे — विशिष्टि
Document Type : Revision
Language : English
Priority : 3
ICS Code : 43.150
Date of Project Approval : 21-08-2023
Standards to be Revised :
Sl.No. Is No & Year
1 IS 2061: 1995
Standards to be Superseded :


Classification Details
Group : Transport and Related Products
Sub Group : Bicycle and Allied Products
Sub Sub Group : Bicycles, bicycle components & Accessaries
Aspects : Product Specification
Risk : Low
Certification : Voluntary Certification
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Commerce and Industry
  • Ministry of Road Transport and Highways
Sustainable development Goals :
  • INDUSTRY, INNOVATION AND INFRASTRUCTURE
Degree of Equivalence : Indigenous
Identical/Equivalent Standards :
Organization Type:

Sl.No. Synosis Points
1 In this revision besides front forks of steel, front forks of all suitable materials including that of aluminium alloy, carbon fibre reinforced polymer, titanium alloy, and magnesium alloy, have been included. Further in this revised standard, fork-shape restrictions have been removed.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 21-08-2023 21-01-2024 05-04-2024 20-08-2024 SHRI SHIVAM AGGARWAL 21-08-2023
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 21-08-2023 -------
2 P-Draft 21-08-2023 Covering letter generated -------
3 P-Draft 21-08-2023 Duration : 30 Days
Remarks : The Document is being P-Draft Circulated for 30 days
TED 16, TED 16,  -------
4 Skipped to W-Draft 06-12-2023 Stage-Changed -------
5 WC Draft 06-12-2023 Duration : 60 Days
Submitted for HOD approval
-------
6 WC Draft 13-12-2023 WC rejected by HOD
Remarks: Please make the necessary corrections as discussed
-------
7 WC Draft 08-02-2024 Duration : 60 Days
Submitted for HOD approval
Remarks : During 30th SC meeting the committee decided to WC the doc for 60 days
-------
8 WC Draft 08-02-2024 WC rejected by HOD
Remarks: Please make the necessary corrections as discussed
-------
9 WC Draft 22-04-2024 Duration : 60 Days
Submitted for HOD approval
-------
10 WC Draft 22-04-2024 WC approved by HOD
TEDC  TED 16, TED 16, -------