Document Details
Name of Department/Committee : LITD 06
Document Number : LITD 06 ( 23347)
Document Title [English] : Passive RF and microwave devices intermodulation level measurement Part 1: General requirements and measuring methods First Revision
Document Title [Hindi] : निष्क्रिय आरएफ एवं सुक्ष्म-तरंग उपकरण, इंटरमॉड्यूलेशन स्तर माप भाग 1 सामान्य अपेक्षाएँ और मापन पद्धतियाँ (पहला पुनरीक्षण)
Document Type : Revision
Language : English
Priority : 3
ICS Code : ICS 33.040.20
Date of Project Approval : 12-06-2023
Standards to be Revised :
Sl.No. Is No & Year
1 IS/IEC 62037 : Part 1: 2012
Standards to be Superseded :
Sl.No. Is No & Year
1 IS/IEC 62037 : Part 1: 2012


Classification Details
Group : Electronic and Telecom equipments, components and devices
Sub Group : Components and accessories for telecommunication
Sub Sub Group : Cables RF LF TV, radio communications
Aspects : Methods of tests
Risk : None
Certification : None
Short Commom Man's Title :
ITCHS Code :
Ministry :
  • Ministry of Communication - Department of Telecommunications
Sustainable development Goals :
Degree of Equivalence : Identical under single numbering
Identical/Equivalent Standards : IEC 62037-1:2021
Organization Type: IEC

Sl.No. Synosis Points
1 This part of IEC 62037 deals with the general requirements and measuring methods for intermodulation (IM) level measurement of passive RF and microwave components, which can be caused by the presence of two or more transmitting signals. The test procedures given in this document give the general requirements and measurement methods required to characterize the level of unwanted IM signals using two transmitting signals. The IEC 62037 series addresses the measurement of PIM, but does not cover the long-term reliability of a product with reference to its performance.

Timeline Details


S.No. P-Draft
Completion Date
WC-Draft
Completion Date
Final-Draft
Completion Date
Project
Completion Date(Gazette)
Entered By Entered On
1 24-08-2023 24-01-2024 01-05-2024 31-10-2024 SHRI BIPIN JAMBHOLKAR 25-04-2024
Stages
Sl.
No.
Stage Date of Occurence Remarks Circulated to Files
1 Generation of Document Number 12-06-2023 -------
2 P-Draft Waived 24-08-2023 The committee decided to issue the standard in wide circulation. -------
3 WC Draft 04-09-2023 Duration : 60 Days
Submitted for HOD approval
-------
4 WC Draft 05-09-2023 WC approved by HOD
LITDC   -------
5 Skipped to Finalization 25-04-2024 Stage-Changed -------
6 Finalization 01-04-2024 ------ -------