Document Details |
|
Name of Department/Committee : | ETD 20 |
---|---|
Document Number : | ETD 20 ( 24500) |
Document Title [English] : | Lightning protection system components LPSC Part 3: Requirements for isolating spark gaps ISGs |
Document Title [Hindi] : | विद्युत संरक्षण प्रणाली कम्पोनेंट्स (एलपीएससी) - भाग 3: स्पार्क गैप को पृथक करने के लिए आवश्यकताएँ (आईएसजीएस ) |
Document Type : | New |
Language : | English |
Priority : | 3 |
ICS Code : | 29.020; 91.120.40 |
Date of Project Approval : | 27-12-2023 |
Standards to be Superseded : |
Classification Details |
|
Group : | Electrical Switchgear and Other Electrical Products/Accessories |
Sub Group : | Electrical installations and general electricals |
Sub Sub Group : | National Electrical Code |
Aspects : | Code of Practice |
Risk : | Medium |
Certification : | Voluntary Certification |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : | |
Degree of Equivalence : | Identical under single numbering |
Identical/Equivalent Standards : | IEC 62561-3-2023 |
Organization Type: | IEC |
Sl.No. | Synosis Points | |
1 | This standard specifies the requirements and tests for isolating spark gaps (ISGs) for lightning protection systems. ISGs can be used to indirectly bond a lightning protection system to other nearby metalwork where a direct bond is not permissible for functional reasons |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 27-12-2023 | ------- | ||
2 | P-Draft Waived | 27-12-2023 | ------- | ||
3 | WC Draft | 27-12-2023 | Duration : 60 Days Submitted for HOD approval |
------- | |
4 | WC Draft | 27-12-2023 | WC approved by HOD |
ETDC ETD 20, | ------- |