Document Details |
|
Name of Department/Committee : | ETD 54 |
---|---|
Document Number : | ETD 54 ( 24544) |
Document Title [English] : | Marine Energy wave tidal and other water current converters Part 20 : Design and Analysis of an Ocean Thermal Energy Conversion OTEC plant General Guidance |
Document Title [Hindi] : | समुद्री ऊर्जा - तरंग, ज्वार और अन्य जल धारा परिवर्तक भाग 20: महासागर तापीय ऊर्जा रूपांतरण (ओटीईसी) संयंत्र का डिजाइन और विश्लेषण - सामान्य मार्गदर्शन |
Document Type : | New |
Language : | English |
Priority : | 3 |
ICS Code : | 27.140 |
Date of Project Approval : | 02-01-2024 |
Standards to be Superseded : |
Classification Details |
|
Group : | Electrical Switchgear and Other Electrical Products/Accessories |
Sub Group : | Renewable energy devices |
Sub Sub Group : | Solar flat plate collector , Water heating system, Solar cooker , Bio gas plant & Biomass cook stove |
Aspects : | Dimensions |
Risk : | Medium |
Certification : | Not Certifiable |
Short Commom Man's Title : | |
ITCHS Code : | |
Ministry : |
|
Sustainable development Goals : |
|
Degree of Equivalence : | Identical under single numbering |
Identical/Equivalent Standards : | IEC 62600-20-2019 |
Organization Type: | IEC |
Sl.No. | Synosis Points | |
1 | This standard general principles for design assessment of OTEC plants. The goal is to describe the design and assessment requirements of OTEC plants used for stable power generation under various conditions. This electricity may be used for utility supply or production of other energy carriers. The intended audience is developers, engineers, bankers, venture capitalists, entrepreneurs, finance authorities and regulators. This standard is applicable to land-based (i.e. onshore), shelf-mounted (i.e. nearshore seabed mounted) and floating OTEC systems. For land-based systems the scope of this document ends at the main power export cable suitable for connection to the grid. For shelf mounted and floating systems, the scope of this document normally ends at the main power export cable where it connects to the electrical grid. |
Timeline Details |
|||||||
|
|||||||
|
|||||||
|
|||||||
Stages |
|||||
Sl. No. |
Stage | Date of Occurence | Remarks | Circulated to | Files |
1 | Generation of Document Number | 02-01-2024 | ------- | ||
2 | P-Draft Waived | 02-01-2024 | ------- | ||
3 | WC Draft | 02-01-2024 | Duration : 60 Days Submitted for HOD approval |
------- | |
4 | WC Draft | 02-01-2024 | WC approved by HOD |
ETDC ETD 54, | ------- |